renovating and building our new permanent home 

100 Bedford Road, Lincoln, MA

We are excited to share construction updates as we convert the Wang family home at 100 Bedford Road into the new permanent home of Birches School. For a tour, please contact Cecily Wardell, Director of Operations, at cecily@birchesschool.org.

Please click here to watch the live feed on our construction cam.

 

Week of November 27, 2017:

IMG_4717.jpg
  • Prepping driveway and parking lot for binder. 
  • Boulder retaining walls built near back addition and on edge of parking lot.
  • Wood chips spread throughout forest play area.
  • Foundations insulated and backfilled in preparation for concrete slab
  • Widened the mouth of the driveway to specifications by the traffic consulting firm.
  • Front of house is regraded in preparation for walkways
  • Work continues on sprinkler system installation.
  • Rough electrical work continues.
  • Rough plumbing continues.
  • HVAC started demo of heating and air conditioning systems in preparation for the new system.
  • Selective demolition and framing continues.
  • Underground plumbing for new addition is installed.
  • Rainwater piping is installed and connected to the drainage system.
  • Interior courtyard is filled to subgrade.
  • Athletic field work is completed until spring seeding.

Week of November 13, 2017:

IMG_1260.JPG
  • Rewiring of electrical system continues with a continued focus on the main house.
  • Work on sprinklers continues, with a focus on the second floor main house.
  • Plumbing work continues
  • Rafters of the caretaker apartment are insulated.
  • Wood framing of walls, windows and doors continues.
  • Floor in a section of the old house is removed in preparation for the classroom floor.
  • Footings and foundation for the front addition and the back addition are formed and filled.

Week of November 9, 2017:

IMG_4179.jpg
  • A huge thank you to to Birches community for clearing the underbrush for our forest play area and prepping the pollinator garden on Saturday!
  • Rewiring of electrical system continues with a continued focus on the main house.
  • Electric conduits for outdoor light poles are installed, inspected, and backfilled.
  • Selective demo of 1940s house continues with a focus on the former kitchen (and future classroom)
  • Rough plumbing continues in the 1940s house.
  • Boulder wall at east side of the parking lot is created. 
  • Prepped the foundation of back addition for concrete forms.
  • Excavated earth for the new front foundation. 
  • Excavated earth for back school and athletic field bathroom.
  • Backfilled the new sewer line after inspection.
  • Trees around the athletic field are planted and work continues on the athletic field.
IMG_4154.jpg

Week of October 30, 2017:

IMG_4090.jpg
  • Rewiring of the electrical system continues with a focus on the main house.
  • Fire alarm wiring begins.
  • Interior selective demo continues with a focus on the main hallway and the former attached garage.
  • Structural framing continues beneath the caretaker apartment.
  • Site work continues with a focus on subgrading for the asphalt binder.
  • Light pole bases for future outdoor lamps are installed.
  • New water service filled and fully tested.
  • Interior plumbing work for waste and water continues.
  • Old foundation on back addition is prepped for concrete work.
  • Athletic field is subgrading and planting for the perimeter of the field are delivered.

 

Week of October 23, 2017:

IMG_3902.JPG
  • Rewiring of the electrical system continues; rough electrical in caretaker apartment finishes.
  • Framing for the caretaker apartment finishes.
  • Interior demo continues with a focus on the former attached garage.
  • Site work continues as we fill and test the new water line to pressure.
  •  The town water line is extended to reach the athletic field bubbler. 
  • New sewer line to new septic system is installed.
  • Work on the sprinkler system continues.
  • Appliances for the new caretaker apartment are delivered.
  • Drain line for the rain garden is installed.
  • New door and windows are framed for caretaker apartment and classrooms.
  • Grass over the septic system continues to thrive.


Week of October 16, 2017:

FullSizeRender (18).jpg
  • Subgrade on parking and driveway is finished.
  • Re-wiring the electrical continues with a focus on the caretaker's apartment.
  • Interior demo continues, including demo of siding to prepare for the front addition.
  • Framing for caretaker's apartment begins.
  • Demo of concrete slab in garage is finished. The former garage will become a classroom.
  • Site work including the rain garden and boulder wall continues.
  • Our new water service is tested in preparation for flushing next week.
  • The team working on the town's athletic field is fully mobilized.
     

Week of October 9, 2017:

FullSizeRender (16).jpg
  • Demo of concrete in back addition begins.
  • Interior demo continues.
  • Sprinkler installation continues.
  • Work begins on the HVAC systems.
  • Re-wiring the electrical system begins and existing light fixtures are removed and stored.
  • Grass is growing in the septic field. 
  • Town of Lincoln continues tree clearing and stumping on the athletic field.
     
FullSizeRender (14).jpg

 

 

Week of October 2, 2017:

  • Chipping ledge for outdoor light pole bases begins.
  • Fire suppression system (sprinklers) installation begins.
  • Front lawn (above septic system) is fully seeded.
  • Concrete slab under the back addition demolition begins.
  • Regrading the parking lot continues as we make a construction path for the construction vehicles needed to build the town athletic field.

Week of September 25, 2017:

FullSizeRender (13).jpg
  • Septic is inspected and backfilled.
  • Water retention areas near the parking lot are inspected and backfilled.
  • Interior demolition continues.
  • Inside electrical work begins.
  • Parts for the fire suppression system are delivered.

 

FullSizeRender (11).jpg

Week of September 18, 2017:

  • Work on the septic continues with septic sand delivery, and delivery of parts for the drip irrigation system.
  • Back roof line is re-sealed after the back addition is demolished to protect against rain and wind.
  • Interior demolition continues.
  • Survey points for the lamp poles are established.
  • Wood chips are piled on the former pool area in preparation for future playscapes.


Week of September 11, 2017:

FullSizeRender (1).jpg
  • The second garage is demolished.
  • The back addition is demolished.
  • The walkway to the back addition is demolished.
  • The pool is crushed and filled in.
  • The fence surrounding the former pool is removed.
  • Septic tanks are installed and digging begins for the septic field. We are using a new technology called "drip irrigation" to ensure as little change to the contours of the front lawn as possible.
  • Grading on the driveway continues.
  • Stormwater and groundwater management systems are inspected and backfilled.
  • Plumbing work on the portion of the house that we are preserving begins.
  • Construction of the rock retaining wall at the far side of the parking area begins.

Fall/Winter 2016/2017 at 100 Bedford Road

FullSizeRender (5).jpg
  • Birches and the Lincoln Land Trust acquire the property at 100 Bedford Road on November 17, 2016.
  • Work begins on documents to submit for Site Plan Review. Documents include footprint of the proposed school building, engineered drawings for the parking and driveway, landscape and lighting details, location for the septic system, and location for the walkways and sidewalks. Documents show conversion of the property from a single family home to a school with parking both for the school during school hours and the proposed athletic field during practice and game hours. 
  • Traffic studies, site engineering, and architectural work begin. 
     

Spring 2017 at 100 Bedford Road

  • Birches School and the Parks and Recreation Department of the Town of Lincoln pass site plan review with the Planning Board of Lincoln to proceed with proposed plans to turn the site into a public-private partnership. Birches School at 100 Bedford Road will provide access and parking for a much needed Lincoln town athletic field. 
  • The town of Lincoln votes unanimously at Town Meeting on March 25, 2017 to fund the purchase of land and the development of 3 acres for the athletic field.
  • Work begins on grading, stormwater and groundwater management systems, and improved visibility for the driveway.
  • Percolation tests are done as work to engineer the septic system continues.
FullSizeRender (6).jpg

Summer 2017 at 100 Bedford Road

  • Architectural and structural drawings for the renovation of retained portions of the Wang property and for the new additions are finalized and permitted for construction.
  • Drip irrigation septic system and reserve area drawings are finalized and permitted for construction.
  • Work continues on grading, stormwater and groundwater management systems, and improved visibility for driveway access.
FullSizeRender (7).jpg

FullSizeRender.jpg

History of our Partnership with The Lincoln Land Trust and the Town of Lincoln

Lincoln is a wonderful place for a nature-based school because about 40% of the town is in conservation and Lincolnites’ passion for the land is almost palpable. The Land Trust (the oldest private land trust in the country) has a visionary staff and, in January of 2016, we signed an MOU with the Land Trust. Approved by the boards of both organizations, the MOU declared that we would collaborate on developing curricular materials and also that the Land Trust would help Birches find a property near conservation land where we could develop informal “outdoor classrooms.” We believe that our formal collaboration with the Land Trust is the first of its kind in the country. In November of 2016, the Land Trust and Birches School purchased a 16-acre property, 9 acres of which has gone into conservation. Our new school is housed on 4 acres, and the remaining 3 acres were purchased by the town of Lincoln in March 2017 to build a badly needed athletic field. We are very grateful that these three Lincoln entities could realize individual goals in a remarkably collaborative way, conserving and making environmentally-sound use of precious land in the Greater Boston area.